SE-AFPB heavy-duty floor expansion joint for 200mm gap

How to Choose the Right Expansion Joint Cover for Your Gap Size (25 mm to 500 mm)

Engineers and site teams usually ask us the same thing: “We have a 100 mm gap on the second floor. What do we use?” Choosing an expansion joint cover comes down to three questions.

  1. How wide is the gap? Measure the actual gap on site; it is often different from the drawing.
  2. Where is it? Floor, wall, ceiling, roof or parking deck.
  3. What will cross it? Foot traffic, hospital beds and trolleys, or cars.

Floor joints: quick selection table

GapRecommended systemLoadFix
25 – 50 mmSE-AFRPB 50 (aluminium + EPDM insert)30 – 300 kNBefore tiling
50 – 55 mmSE-AFPA 50 surface cover30 kNAfter tiling
75 – 100 mmSE-AFPA 75–100 sliding cover5 kNAfter tiling
25 – 200 mmExtruded aluminium cover 4–5.2 mm30 – 300 kNAfter tiling
200 mmSE-AFPB heavy-duty, 6 mm plate500 kNBefore tiling
50 – 300 mmSS 304 parking / podium jointVehicleEither
100 – 300 mmGI centre plate system with EPDM30 – 300 kNBefore tiling
SE-AFRPB 50 floor expansion joint with EPDM rubber insert
SE-AFRPB 50: twin aluminium profiles with an EPDM insert, set flush with the tiles

Wall and ceiling joints

Walls and ceilings don’t carry traffic, so the choice is mainly about looks and how much the joint moves:

  • 25 – 100 mm: SE-AW clip profile. It presses in with spring-steel clips and has no visible screws.
  • 25 – 250 mm: SE-AWC powder-coated cover, available in any colour to match the façade.
  • 50 – 300 mm: wall/ceiling cover profile on GI self-aligning clamps, for ±25 mm movement on seismic façades.

Roof joints

Roof joints must be watertight first and good-looking second. We bond an EPDM barrier into the gap with Mapei Adesilex epoxy, then fit an aluminium L-profile and top cover. This works for 25 – 200 mm gaps with ±25 mm movement.

Before or after tiling?

This matters for programming the work. Flush systems such as SE-AFRPB and SE-AFPB are fixed before the floor finish, so the tiler works up to them. Surface covers such as SE-AFPA go on after tiling. If the floor is already finished, a surface cover is usually the only practical option.

Tip: always ask the structural consultant for the expected movement (±mm) as well as the gap width. Two 100 mm joints can need very different systems.

Need help choosing a joint for your project? Send us the joint width and location or call +91 98187 49056. We usually reply with a recommendation the same day.

Share this guide:WhatsAppLinkedInFacebookX

Leave a Comment

Your email address will not be published. Required fields are marked *