Our installation teams have fitted floor, wall and roof joints at hospitals, hostels, colleges and corporate campuses. This is the sequence they follow, written so site engineers know what to expect and what to check.
1. Before we arrive
- The structural gap is cleared of shuttering, debris and thermocol
- Edges of the gap are straight and sound, with no honeycombing
- The finished floor level (FFL) is marked so profiles can be set to the right height
- For flush systems, tiling hasn’t started near the joint yet
2. Floor joints
- Clean both edges of the joint and check the depth; most flush systems need at least 40 mm
- Fix the EPDM moisture barrier across the gap with epoxy
- Set the aluminium base profiles to the FFL and check them with a spirit level
- Anchor with stainless steel screws, 6 × 50 mm or 8 × 77 mm, at 300–400 mm centres
- Fit the centre plate or insert with its self-centring bar
- Tile or lay granite up to the profile edges
- Clean, check movement and hand over
3. Wall and ceiling joints
For clip profiles, the spring-steel clips go into the dovetail at the back of the profile: 5 per 3 m bar on walls and 7 on floors. The profile is then pressed evenly into the joint. For screw-fixed covers, we fix one side through round holes and the other through oblong holes so the plate can slide.
4. Common mistakes we fix
- Both sides of a cover plate screwed tight, which locks the joint so it cracks
- Sealant used instead of an EPDM barrier
- Profiles set to the wrong level, leaving a lip that people trip on
- Tiles grouted right into the movement gap
- Anchors too close to the slab edge, which spalls the concrete
Ask for a short handover note with photos of the EPDM before the covers go on. Once the plates are fixed, you can’t see it.